SLI Project Time Line
Home - Timeline - Team Members - Photos
August 2006:
16: Request for proposal goes out to all schools.
October 2006:
2: One hard copy and one electronic version of the completed proposal due to NASA/MSFC.
16: Awards granted. Schools notified of selection.
23: SLI teams teleconference.
30: NASA media announces new 2006-2007 SLI Teams.
November 2006:
13: Web presence established for each team.
20: Preliminary Design Review
First (PDR) Report due.
27: PDR Discussion
January 2007:
22: Critical Design Review Presentation Slides
Second (CDR) Report due.
29: Critical Design Review: Submit Invoice
March 2006:
19: Flight Readiness Review Presentation Slides
Third (FRR) Report due.
26: Flight Readiness Review: Submit Invoice
April 2007:
25: Travel to Huntsville
26: Rocket Fair
28: Launch Day
29: Travel Home
May 2007:
25: Final Report due: Submit Invoice